Topic: Critical Path
The Critical Path represents the sequence of tasks or events that
directly effect the completion of a project. Knowing the Critical Path
allows the project manager to shorten or at least control a project's
schedule by focusing on those tasks which directly affect the
project's completion. This is called Critical Path Management.
In the simple example at above, Tasks 2 and 3 both start when Task
1 is complete, and Task 4 starts when tasks 2 and 3 are both complete.
Since Task 2 takes 5 days, and Task 3 tasks only one day, it is
obvious that Task 2 drives the start of Task 4, and thus the
completion of the project.
The Critical Path in this example is the sequence of tasks 1, 2,
and 4. If any one of those lengthens (or shortens) by a day, the
project's completion will change by that amount.
Up to a point Task 3's duration does not affect the project
completion; Task 3 is said to be 'Off the Critical Path". However, if
Task 3 were to change to 6 days duration, it would now dictate the
start of Task 4; Task 3 would be On the Critical Path, and Task 2
would be Off.
It is common practice in this type of software to identify the
Critical Path in RED to make it stand out, as shown in the diagram.
The way to shorten a project's schedule is to focus on shortening
the duration of the tasks on the critical path (i.e. paying more for
expedited delivery of a crucial component.)
Note: You can't make the Critical Path go away. - No
matter how hard you work to shorten your projects schedule, the
software will still always show a critical path somewhere. Shortening
some tasks just moves the critical path over to other tasks that
haven't been optimized yet.
Next Topic - Gantt Charts
Tutorial Home |